Welcome! Log In Create A New Profile

Advanced

#19 work continues.

Jim Burrill
July 05, 2000 06:36PM
Well, I read where Mike O. stopped by the shop on Sunday afternoon. Mike, I apologize, I left the shop at about 12:30 PM Sunday for a drive up the Conejos Canyon. It was a beautiful trip.
Anyway, we did indeed fire up the #19 on Monday, but we encountered a difficulty with either the fuel pump or else the governor. The locomotive ran for about an hour, idling, and then the #1 prime mover began to race. I pulled the shutoff lever inside the cab and it didn't have any effect. George and I were both pretty bummed about that, because I had visions of a July 4th photo out on the line somewhere.
We'll be back down there this coming weekend. We left #19 outside the shop so that Marvin Casius or whoever needs to use that space inside the shop will be able to do that.
I had an email exchange with John West, and it seems that the finances on the railroad are not as rosy as hoped at one point. We all hope this changes soon. It may influence the ability to finish #19 in a complete fashion.
Oh, there still is an issue where one of the traction motors has an overload condition in one direction only. We may still have to lock out that motor for a temporary fix.
Jim Burrill
Subject Author Posted

#19 work continues.

Jim Burrill July 05, 2000 06:36PM

Oops

John West July 05, 2000 09:02PM

Re: Misunderstanding, sorry.

Jim Burrill July 05, 2000 10:05PM

Re: #19 work continues.

Mike Oestreich July 05, 2000 11:09PM

Re: #19 work continues.

Boris Serena July 05, 2000 11:33PM

Re: #19 work continues.

Jim Burrill July 06, 2000 07:39AM

Re: #19 work continues.

Roger Mitchell July 06, 2000 08:33AM

Re: #19 work continues.

Jim Burrill July 06, 2000 08:44AM



Sorry, you can't reply to this topic. It has been closed.