Welcome! Log In Create A New Profile

Advanced

Mud Tunnel Challenges 2000-2004

August 11, 2012 05:21PM
Cole, as you can gather from Earl's post, the unstable and shifting nature of the strata which Mud Tunnel goes through has been a serious problem for the C&TS, and likely for the D&RGW ever since the line was constructed.

Notwithstanding the considerable work done in the eighties to correct the serious problems described by Earl, by 2001 the tunnel was again becoming a threat. In November an FRA inspector identified serious deterioration in bents and liners at both ends and evidence that the strata had been shifting. The inspector also recommended tension gauges be installed to measure any shifting.

The FRA assessment was no surprise because back in 2000 RGRPC had worked with the track and tunnel engineering firm, Milbor-Pita, on a series of recommendations to the Commission to correct the tunnel's increasing instability. Some work was authorized by the Commission using monies from an EDA trackwork grant, but there was little progress, so come May of 2002 the FRA requested the Commission suspend passenger train service due to lack of progress on the tunnel and problems at Martinez Point and other locations.

By August the Commission had submitted plans acceptable to the FRA, and train service resumed, but with close monitoring of Mud Tunnel. Eventually by September of 2004 the Commission and tunnel contractor, Centennial Engineering, thanks in part to EDA grants, completed over $200,000 in extensive reinforcement and strengthening of the tunnel, the results of which you see today. As I recall the man in charge was an Aussie mining tunnel engineer. As far as I know the work has been successful, but keep your fingers crossed.
Subject Author Posted

Question Regrading Work That Has Been Done To Mud Tunnel Since D&RGW Ownership

chamafun463 August 10, 2012 01:14PM

Re: Question Regrading Work That Has Been Done To Mud Tunnel Since D&RGW Ownership

drgwk37 August 10, 2012 02:25PM

Re: Question Regrading Work That Has Been Done To Mud Tunnel Since D&RGW Ownership

chamafun463 August 10, 2012 02:57PM

Re: Question Regrading Work That Has Been Done To Mud Tunnel Since D&RGW Ownership

Greg Scholl August 10, 2012 03:09PM

Re: Question Regrading Work That Has Been Done To Mud Tunnel Since D&RGW Ownership

Earl August 11, 2012 08:26AM

Re: Question Regrading Work That Has Been Done To Mud Tunnel Since D&RGW Ownership

Steve Forney August 11, 2012 09:47AM

Re: Radical Rationations Regarding Retro-Regrading @ Mud Tunnel ... eye popping smiley

Russo Loco August 12, 2012 01:34AM

Re: Radical Rationations Regarding Retro-Regrading @ Mud Tunnel ... eye popping smiley

Steve Forney August 12, 2012 07:25AM

Re: Radical Rationations Regarding Routinely Retro-Regrading Roundabout Railroad Routes ... eye rolling smiley

Russo Loco August 13, 2012 08:58PM

Re: Radical Rationations Regarding Routinely Retro-Regrading Roundabout Railroad Routes ... eye rolling smiley

Steve Forney August 13, 2012 09:09PM

Re: Radical Rationations Regarding Routinely Retro-Regrading Roundabout Railroad Routes ... eye rolling smiley

chamafun463 August 13, 2012 09:13PM

Re: Question Regrading Work That Has Been Done To Mud Tunnel Since D&RGW Ownership

chamafun463 August 11, 2012 05:19PM

Mud Tunnel Challenges 2000-2004

Dick Cowles August 11, 2012 05:21PM

Re: Question Regrading Work That Has Been Done To Mud Tunnel Since D&RGW Ownership Attachments

ROW Explorer August 11, 2012 06:53PM

Re: Question Regrading Work That Has Been Done To Mud Tunnel Since D&RGW Ownership

chamafun463 August 11, 2012 07:02PM

Re: Question Regrading Work That Has Been Done To Mud Tunnel Since D&RGW Ownership(Post Addition Made)

Dick Cowles August 12, 2012 03:48PM

Re: Question Regrading Work That Has Been Done To Mud Tunnel Since D&RGW Ownership(Post Addition Made)

C. Llamas August 13, 2012 01:15PM



Sorry, only registered users may post in this forum.

Click here to login