I have seen several of these reports where work engines describe "used 3 tons of coal". Can you tell me why this is on these reports? Thanks.

Projects such as these were authorized by AFE, Authority For Expenditure. Each AFE was budgeted for a specified amount, the estimated cost amount.

Every expense involved with an AFE was charged to that AFE.

Those charges would include wages of employees working in connection with the AFE, section men, equipment operators, train crews, ditcher engineer, tools, material, etc. The amount of coal used was recorded in order that it be priced out and charged to the AFE.

Jimmy
Subject Author Posted

Alamosa September 1 1936

Jimmy Blouch September 02, 2011 10:17PM

Re: Alamosa September 1 1936

CharlieMcCandless September 03, 2011 03:32AM

Re: Alamosa September 1 1936

Tomstp September 03, 2011 09:46AM

Re: Alamosa September 1 1936

Jimmy Blouch September 03, 2011 09:31PM

Re: Alamosa September 1 1936

Tomstp September 03, 2011 10:22PM

Re: Alamosa September 1 1936

drgwk37 September 03, 2011 12:46PM

Re: Alamosa September 1 1936, pass car nit

hank September 14, 2011 11:36AM

Re: Alamosa September 1 1936, pass car nit

Jimmy Blouch September 14, 2011 02:05PM

Re: Alamosa September 1 1936

Ryan Morris April 08, 2019 07:31PM



Sorry, only registered users may post in this forum.

Click here to login