March 08, 2001 01:46PM
From the news page, it says 497,487,489 and 463 should be ready in April. 484 or 488 should be ready be the end of May.
Engine 497, once arch bricks are installed, will be ready for service.
Engine 487 will have repaired axle crank pins installed as well as some boiler tubes repaired. It is expected to be serviceable by early April.
Engine 489 is expected to be in service about early April.
Engine 463 is expected to be mid- to late April.
Engine 484 and 488 are both in progress. One or the other of them is expected to be ready by mid-May.