This is the summery of this years Team Leader report covering the progress made on the car



COOK CAR 053 - Project 1003



1. Team Leader: Jim OKeefe


2. Work Sessions: B (1 day only, not on schedule), C (1 day only, crew diverted to DBG 859 and shop organization),
D (1 day only, crew diverted to shop organization and door repair), E, F


3. The team: B - Jim OKeefe, Russell Sparks

C - Jim OKeefe, Bob Mundis, Peter Dulong

D - Jim OKeefe

E - Jim OKeefe, Laura Evans, Howard Bunte, Jim Cook, Lee Harp

F - Jim OKeefe, Laura Evans, Art Evans* Bill Kepner, Chase Kepner (JV)**, Bill Barbour, Barb Hutchison**, Hutch Hutchison
*worked several days, was actually assigned to DBG 724
**Assisted with Flat Car 6544 as needed

Phil Hackman***, Wade Hall**** – Reassigned to Flat Car 6544
***Phil Hackman will submit a team leader report covering the Flat Car 6544 work
**** Volunteered Monday – Wednesday Only

4. The Objective: Remove siding. Survey Car to determine sill work required. Place orders for materials to complete sill work
and car residing. Finish interior work started by Laura Evans. Repair sill as needed. Fabricate and install sill reinforcement.
Start siding install as time allows.


5. The work: B - 70% of siding remove.

C - Siding removal completed, damaged car steps repaired

D - Survey completed by Art Randall, Don Bayer, Marvin Casias, and Jim OKeefe. Survey report completed and material
order for sill reinforcement steel prepared.

E - Interior Painting 70% completed, oil cloth made to cover table, Wood and steel deliveries secured in the building,
½” X 6” steel cut to length, one short reinforcement section fabricated

F - All interior painting except the floor completed, original cabinet/draw/door hardware reinstalled, 50% of the
false floor removed, one sill repair splice fabricated and installed. Steel reinforcement fabrication continued – one
long section 90% complete and drilling of other sections continued.


6. Project Status: The project is far from complete I at the current rate I would expect completion in three to four years.
If crews of 5 to 6 can be provided each work session this estimate can be revised.

Work will continue on the sill repairs and reinforcement. As the outer sill on each side if completed, siding of that side can proceed.
Subject Author Posted

Cook Car 053

drgw480 October 31, 2007 06:34PM

Re: Cook Car 053 Attachments

drgw0579 October 31, 2007 07:09PM

Re: Cook Car 053 Attachments

Russo Loco November 01, 2007 02:22AM

Re: Cook Car 053 Attachments

drgw0579 November 01, 2007 07:18AM

Re: Cook Car 053

Pat November 01, 2007 10:43AM

Re: Cook Car 053

Anonymous User November 03, 2007 06:41PM

Re: Cook Car 053

Jim November 05, 2007 08:03AM



Sorry, only registered users may post in this forum.

Click here to login