The schedule of 2010 work sessions has been posted to the Friends of the East Broad Top website:
Friends of the East Broad Top Restoration Projects
Here are the dates, cut and pasted from the FEBT website:
2010 Rockhill Furnace Work Schedule
January 16-17
February 13-14
March 13-14
April 17-18
May 15-16
May 17-21 (work week) (Probable)
June 5-6
June 26-27
July 24-25
August 14-15
September 11-12
November 13-14
November 7-8
2010 Robertsdale Work Schedule
January 23-24*
February 20-21*
March 20-21*
April 17-18
May 1-2
May 15-16
June 5-6
June 19-20
July 3-4
July 17-18
August 7-8
August 21-22
September 4-5
September 18-19
October 16-17
November 6-7