Day 1 of the WW&F Track laying weekend:
There was a crew of about 20 or so by the end of the day. 180 feet of track was spiked to the north end of the main line (about where the north switch begins for the Alna Center run-around track) and another 100 or so feet of ties were extended further along. The crew also shoveled gravel off the flatcar for the southern end of the siding. At the end of the day a crew was working to assemble the southern switch.
3 more days of great weather is forecasted - do come out and assist if you can.
James Patten
WW&F
Subject Author Posted

WW&F Track Laying Day 1 *LINK*

James C Patten October 08, 2004 05:16PM

Re: WW&F Track Laying Day 1

Karasu October 09, 2004 03:21PM

Re: WW&F Track Laying Day 1

James C Patten October 09, 2004 06:37PM

Re: WW&F Track Laying Day 1

Pat October 10, 2004 10:15AM

Re: WW&F Track Laying Day 1

Ted Miles October 10, 2004 08:49PM

Re: WW&F Track Laying Day 1

James C Patten October 11, 2004 07:20PM



Sorry, you can't reply to this topic. It has been closed.