The engineering was done and signed off on, after we had the contractor go back to the engineer and re-design for the extra heavy snow load expected in Silverton.
Wind load I do not know for sure about. That discussion never came up. I assume that the structural engineer took that into consideration, especially after we had him ( engineer) re-design for the added snow loading. He was well aware of its finished location.

Dave T.
DRHS BOD
Subject Author Posted

DRHS Railcar Display Shed 9/19/20 Attachments

Joe Weigman September 19, 2020 10:13PM

Re: DRHS Railcar Display Shed 9/19/20 unrelated RR park photos Attachments

Joe Weigman September 19, 2020 10:19PM

Re: DRHS Railcar Display Shed 9/19/20 unrelated RR park photos

nedsn3 September 20, 2020 07:52AM

Re: DRHS Railcar Display Shed 9/19/20 unrelated RR park photos

John Cole September 20, 2020 08:34AM

Re: DRHS Railcar Display Shed 9/19/20 unrelated RR park photos

Joe Weigman September 20, 2020 09:22AM

Re: DRHS Railcar Display Shed 9/19/20

Hauspiper September 20, 2020 09:28AM

Re: DRHS Railcar Display Shed 9/19/20

Joe Weigman September 20, 2020 09:39AM

Re: DRHS Railcar Display Shed 9/19/20

Hauspiper September 20, 2020 09:53AM

Re: DRHS Railcar Display Shed 9/19/20 Attachments

Jerry474 September 20, 2020 09:23PM

Re: DRHS Railcar Display Shed 9/19/20

Joe Weigman September 20, 2020 10:02PM

Re: DRHS Railcar Display Shed 9/19/20

Herb Kelsey September 20, 2020 11:52PM

Re: DRHS Railcar Display Shed 9/19/20

Joe Weigman September 20, 2020 11:59PM

Re: DRHS Railcar Display Shed 9/19/20

jim pallow September 20, 2020 03:47PM

Re: DRHS Railcar Display Shed 9/19/20

dave2-8-0 September 20, 2020 06:30PM

Re: DRHS Railcar Display Shed 9/19/20

jim pallow September 21, 2020 07:16PM