Gunnison-Boiler House & Pump House

March 01, 2001 11:26AM
From engineering report page 292 item 9:
Structure # 32
Boiler House, frame 26'x52'x17', 22984 Cu.ft.comp roof, $919.00
Foundation $32.00
Mechanical Eq.and pipe lines $1485.00
Equipment $61..00
Total $2497.00
AFE #1890 1924
Add lighting-open knob & clete type, switch and cut leads in conduit, 2-outlets $8.27
AFE #4892 1931
Retire part item 9 page 292 ER(not mech.eq.)
Construct new Boiler House 38'x20'x14', 10640cu.ft.
Foundation-fir blocking (2.200mbm).
Walls-2nd hand corr. iron on 2x6"-2' ctrs., not trussed, 6" overhang.
Openings-3 windows 12"x16", 8 lights.
Floor- common brick paving
Total $495.52
AFE #T451 1947
Retire from ER page 292 item 9. Portion of mechanical Eq. & pipe lines:
General service pump, Simplex steam Cameron #9, size 12"x7"x13".
Pump foundation "b" lumber .150mbm.
Steam supply 2" WIP-24 lin.ft..
1-1 1/2", & 1-2" globe valve.
Exhaust-2" WIP 16 ln.ft..
1 Qt. lubricator.
Cameron #8 aux. pump.
Foundation "c" lumber .100mbm.
Steam line 1 1/2" WIP-8 lin.ft..
1 1/2" globe valve.
Exhaust-2" WIP-10 lin.ft..
Suction pipe 4" WIP-16 lin.ft..
2-4" ells.
Discharge 3" WIP.1 lin.ft..
3" gate valve.
Line to building 20 lin.ft. of 2 1/2" WIP.
1-2 1/2" ib globe valve.
1-1 1/2" Br. hose connection.
2-2 1/2" ells.
Drain 90 lin.ft. of 8" VCP.
(Remainder of Mech. eq. & pipe lines, transferred
to Engine House-structrue #26, into the Brick Boiler House Leanto addition. 5-11-49)
Next week: the new Pump House & the Roundhouse