June 10, 2018 05:26PM
Below are a series of pictures I took on Saturday, 6/10, showing what was accomplished during seven says of intense work in Como.

This photo shows the 60' of track that was added beyond the depot towards the hotel. This allows the engine, and multiple cars, to clear the switch.

_MG_9595F.jpg


Below is the C&S gondola we received on Wednesday.

_MG_9599F.jpg


Below you can see the freshly repainted, C&S boxcar that we use for our tool shed.

_MG_9604F.jpg



Below is the 120' of track added to the mainline towards Gunnison. It ends next to the water tower foundation. This is where the gondola was unloaded.

_MG_9607E.jpg


Here I am looking at the end of track farther back showing the driveway to the roundhouse. There is a rough area we have to cross next and then the driveway. This will require extensive "landscaping."

_MG_9609E.jpg



Edited 13 time(s). Last edit at 06/16/2018 07:08PM by John Meixel.
Subject Author Posted

Como Work Week Results Attachments

John Meixel June 10, 2018 05:26PM

Re: Como Work Week Results

Michael Moore June 10, 2018 05:55PM

Re: Como Work Week Results

Prowordsmith June 10, 2018 05:56PM

Re: Como Work Week Results Attachments

John Meixel June 10, 2018 06:20PM

Re: Como Work Week Results

Jerry Huck June 10, 2018 08:04PM

Re: Como Work Week Results

Jason Midyette June 10, 2018 08:32PM

Re: Como Work Week Results thumbs up

Stewart Rhine June 10, 2018 09:05PM

Re: Como Work Week Results. Track Finishing pt. 1 Attachments

Jeff Ramsey June 11, 2018 02:28AM

Re: Como Work Week Results. Track Finishing pt. 2 Attachments

Jeff Ramsey June 11, 2018 02:50AM

Re: Como Work Week Results. Track Finishing pt. 2

Stewart Rhine June 15, 2018 07:59PM

Re: Como Work Week Results

jim pallow June 16, 2018 05:43AM