Re: C&S 9 status

July 01, 2009 12:19PM
Okay guys,

I swore I would never post again. The contract has not been changed on the #9 other than there are issues with the preparation for the site for the engine. I wish I knew of a change in the contract as it would of saved a lot of work, time and money. In many cases we are doing far more than the contract called for.

The engine was to be made serviceable for Breckenridge. At the time of the contract we knew the boiler had major issues. There was no way the FRA would ever accept it unless somebody was willing to really lie about it. The external corrosion should of not allowed it to go back into service for 2006. The state condemned it after 2006. We spent a great deal of time and effort getting a variance to operate her at 145 psi from the state. That variance was granted. With annual inspections she can keep that pressure for a long time to come.

The next issue which is a deal breaker is the cracks in the cylinder area below the saddle which cracks wrap all the way under the cylinder center section. Not only are there old cracks which an attempt was made to repair then there are new cracks starting. This is something that should of shown up in 2006 had somebody actually taken the time to clean the old girl. These cracks are deal breakers. She will never run in her current state except under a very minimal load. Otherwise its only a matter of time before the cylinders become a kit.

Now as far as the work we have done. New crown brasses, reworked the boxes, replaced some hub liners, turned journals, turned tires, new shoes and wedges, cylinder bore work, new pistons, new piston rods, new packing, slide valve work, the above boiler work, throttle work(it leaked like a rusty bucket)branch pipe work(they leaked like the same bucket), all new gaskets for these parts, crosshead work, rebuild lead truck, new lead truck wheels, new hub liners, renew lead truck journals, babbit and cut the lead truck brasses, lead truck box work, swing link work on lead truck, rebuild brake cylinders, some spring work, brake pins and bushings, made the rods brite, new rod bearings and bushings and we are working on the valve gear right now.

The whole engine has been sandblasted and is painted with both imron primer and high gloss black inron, the cab is being refinished with quality paint as the roof was already coming off from the weather along with the paint peeling.

We still have jacket paint to do and the piping. We have spent $10,000 just on air compressors and sand. One employee spent a month making the rods look good. Its going on its wheels in a couple of days.

The running gear will be very sound, the brakes sound, the springs sound, the boiler so so because of its overall condition, the valve gear decent. Cosmetically she has the best paint money can buy and the prep work has been the best possible. Sandblast to clean metal.

John Braun
Subject Author Posted

C&S 9 status Attachments

KoloradoKid June 30, 2009 04:02PM

Re: C&S 9 status

jalbers June 30, 2009 04:05PM

Re: C&S 9 status

FordCVP71 June 30, 2009 04:08PM

Re: C&S 9 status

southparkline1 June 30, 2009 04:29PM

Re: C&S 9 status

FordCVP71 June 30, 2009 04:56PM

Re: C&S 9 status

southparkline1 June 30, 2009 05:45PM

Re: C&S 9 status Attachments

Jason Midyette June 30, 2009 06:03PM

Re: C&S 9 status

southparkline1 June 30, 2009 06:16PM

Re: C&S 9 status

Dan Robirds June 30, 2009 06:38PM

Re: C&S 9 tender status

Russo Loco June 30, 2009 08:58PM

Re: C&S 9 tender status

Tim Schreiner June 30, 2009 09:28PM

Re: C&S 9 status

jasonsobczynski July 01, 2009 11:02AM

Re: C&S 9 status

FordCVP71 July 01, 2009 11:11AM

Re: C&S 9 status

locoboilerguy July 01, 2009 12:19PM

Re: C&S 9 status

FordCVP71 July 01, 2009 12:29PM

Re: C&S 9 status

mransr July 01, 2009 08:25PM

Re: C&S 9 status

gbrewer July 01, 2009 01:46PM

Re: C&S 9 status

Russo Loco July 01, 2009 03:46PM

Re: C&S 9 status

KoloradoKid July 01, 2009 03:54PM

Re: C&S 9 status

southparkline1 July 01, 2009 04:24PM

Re: C&S 9 status

locoboilerguy July 01, 2009 04:29PM

Re: C&S 9 status

Skip July 02, 2009 06:03PM

Re: C&S 9 status

southparkline1 July 02, 2009 06:09PM

Re: C&S 9 status

Jason Midyette July 01, 2009 04:25PM

Re: C&S 9 status

Russo Loco July 01, 2009 04:51PM

Re: C&S 9 status

gbrewer July 01, 2009 05:45PM

Re: C&S 9 status

Donald Foster July 01, 2009 06:54PM

Re: C&S 9 status

Rick Steele July 01, 2009 06:57PM

Re: C&S 9 status - OUCH!

Russo Loco July 01, 2009 08:46PM

Re: C&S 9 status - OUCH!

southparkline1 July 01, 2009 09:19PM

Re: C&S 9 status - OUCH!

Rick Steele July 02, 2009 08:13AM

Re: C&S 9 status

Jason Midyette July 01, 2009 04:16PM

Re: C&S 9 status

Samart July 01, 2009 05:36PM

Re: C&S 9 status

southparkline1 July 01, 2009 06:10PM

Re: C&S 9 status Attachments

locoboilerguy July 02, 2009 12:01PM

Re: C&S 9 status

chris king July 02, 2009 02:11PM

C&S 9, some different questions

Steve G. July 02, 2009 03:04PM

Re: C&S 9, some different questions

locoboilerguy July 02, 2009 04:04PM

Re: C&S 9, some different questions

KoloradoKid July 03, 2009 12:44PM

Re: C&S 9 status

jasonsobczynski July 04, 2009 12:19AM

Thank you

Festus July 15, 2009 12:18PM

Re: C&S 9 status

KoloradoKid July 10, 2009 04:24PM

Re: C&S 9 status

locoboilerguy July 15, 2009 09:02AM

Re: C&S 9 status

KoloradoKid July 20, 2009 09:30PM

Re: C&S 9 status

locoboilerguy July 22, 2009 03:58PM

Re: C&S 9 status

KoloradoKid July 22, 2009 04:11PM

Re: C&S 9 status Attachments

KoloradoKid July 22, 2009 09:04PM

Re: C&S 9 status

Tim Schreiner July 22, 2009 09:07PM



Sorry, only registered users may post in this forum.

Click here to login