Welcome! Log In Create A New Profile

Advanced

The CASE for mandatory inspections!

August 23, 2001 10:54PM
Here is the first of several official reports that will be released on the Medina boiler explosion. It makes for sobering reading. Read especially his last paragraph!
Examination Report On The Antique Boiler That Exploded In Medina, Ohio On July 29, 2001
John D. Payton, Director Boiler Section
I am the Director of the Certified Boiler Engineers for The Commonwealth of Pennsylvania and have conducted an inspection of a boiler explosion of an Antique Boiler at Medina, Ohio. This inspection and evaluation was conducted at the request of the Medina County Sheriff Mr. Neil F. Hassinger and Lieutenant John Detchon.
I was briefed on August 6 about 1300 by Lieutenant Detchon and he informed me that the safety relief valve has been removed by Chief Dean Jagger, the chief boiler inspector of the State of Ohio, and sent to the National Board for inspection and testing. He stated that the seals were intact on the valve and that the National Board test lab's initial report stated that the valve did not lift with pressures up to 200 psi. This exceeded the set pressure of the valve of 125 psi. The pressure indicator was also tested in the same lab and found to indicate 25 psi. lighter, meaning the pressure could be 25 psi. higher than the indicator reads. Chief Jagger also removed part of the damaged "crown" sheet and the fusible plug. The crown sheet and fusible plug were sent to Case Western Reserve University for a metallurgical examination. Lieutenant Detchon also stated that the fusible plug shows slight signs of overheating, however it did not melt and blow out. Lieutenant Detchon's investigation revealed that the late owner had purchased some type of boiler sealer. It could be safe to assume that the late owner knew that the boiler was leaking and attempted to seal the leaks with this compound. I have accepted Lieutenant Detchon's statements as fact and started my examination of the boiler parts that were available for inspection and I found the following conditions:
The staybolt holes in the crown sheet showed a maximum engagement of threads of 2.5 threads and often the least amount of engagement was 1.5 threads. The original design of thread engagement was 4.5 threads in a 3/8" crown sheet thickness. There were at least 5 stays that had been welded around the threaded area because of excessive loss of metal in the crown sheet. The crown sheet shows excessive amounts of corrosion throughout the total surface area. The area around the threaded stays showed more reduction of thickness because this is a high stress area. The problem is compounded because the less the thickness the higher the stress. Measurements conducted show a thickness of .210", .170", .125",
.105" and .085". The original design thickness was .375".
The original staybolts were 1" in diameter and appear to be 11 threads per inch by measurement with a thread gauge. The condition of the stays in the crown sheet area is one of uniform deterioration and confirms the thread engagement in the crown sheet of not more than 2.5 threads and as low as 1.5 threads of engagement. The diameter of the stays in the corroded area is between .600" and .700". This is a reduction of 64% of the cross sectional area of the staybolt. The staybolts position in the wrapper sheet, with exception of approximately 5 staybolts, were in the original position indicating the ease that the crown sheet separated from the stays. The pitch of the stays as was measured in the crown sheet was 4.5" and this was confirmed by measuring the staybolts in the fire box.
The computations using various formulas ASME 1924 and ASME 1998 computed using a thickness of .085" came out to be between 40 psi. & 47 psi. I also used a carbide type scriber to test surface hardness. I noticed that there was no difference between the steam dome, the barrel and the ruptured crown sheet. This test is not conclusive but an indicator of the metal condition.
The ASME code requires that when the fusible plug is installed, the fusible plug must remain at least 1" above the crown sheet. The plug design was proper and met the requirement as confirmed by Lieutenant Detchon. Inspection of the hand hole plug above the crown sheet revealed that the plug has not been removed recently as the threads were rusted. The area shows improper inspection of the crown stays. The front tube sheet hand hole plug threads were corroded revealing that the plug had not been removed recently. This plug allows the removal of scale and inspection of the condition of the barrel.
CONCLUSION
It is my evaluation of this boiler that the crown sheet failure started at the .087" thickness area, the weakest point in the crown sheet, and this is where the most bending damage is done to the sheet. The rest of the sheet shows signs of being peeled away much as peeling wall paper off of a wall. This was caused by the massive expansion of released steam. It is my evaluation that because of the very poor condition of the crown sheet with the reduction of the original thickness from .375" to .087" leaving only 23% of the original thickness; this was insufficient metal to hold the pressure of the steam resulting in a mechanical failure of the boiler. To further explain, the thinning of the crown sheet allowed the crown sheet to slightly bag in between the staybolts. This bagging allows scale to build up in these pockets or bags that insulate the metal from the cooling of the boiler water. This further compounds the bagging by localized overheating until there is failure of the crown sheet. This explains how the sheet could be slightly overheated without melting the fusible plug and does not support the theory of a Boiling Liquid Expanding Vapor Explosion (BLEVE).
Professor Wallace's Report supports the bagging theory as some parts of the crown sheet shows signs of overheating while others do not. I estimate the amount of energy released during the explosion at 90 psi. to be around 28,000,000' lbs of force of which approximately 1,280,000' lbs was used to lift the engine and the remaining was dissipated in the blast area around the engine.
The inoperative safety valve had no direct bearing on the explosion as the valve was set for 125 psi. and with the condition of the crown sheet. It is doubtful that pressure was attainable. I further conclude that, had the boiler been presented for inspection in Pennsylvania, the boiler would have been placed out of service and not allowed to operate.
John D. Payton, Director
Boiler Section
Subject Author Posted

The CASE for mandatory inspections!

Michael Allen August 23, 2001 10:54PM

Re: The CASE for mandatory inspections!

nymph August 23, 2001 11:18PM

Re: The CASE for mandatory inspections!

HRMO'Biph August 24, 2001 06:54AM

Re: The CASE for mandatory inspections!

Mik August 24, 2001 07:57AM

Re: The CASE for mandatory inspections!

Michael Allen August 24, 2001 05:19PM

For the record.

Mik August 24, 2001 08:25PM

Re: For the record.

Michael Allen August 24, 2001 11:31PM

Inspections

Mik August 25, 2001 12:21AM

Re: For the record.

HRMO'Biph August 25, 2001 08:10AM

Re: For the record.

Jim Adams August 26, 2001 03:08PM

Re: For the record.

Michael Allen August 26, 2001 08:40PM

hydro testing

Mik August 26, 2001 09:34PM

Oops

Mik August 28, 2001 12:00PM

Re: The CASE for mandatory inspections!

C.H.Irvin August 26, 2001 08:22AM

Re: The CASE for mandatory inspections!

Tom Stewart August 24, 2001 09:19AM

Re: Boiler repair by plating

Bob Keller August 24, 2001 09:42AM

Re: Boiler repair by plating

Tom Stewart August 24, 2001 10:06AM

Re: Boiler repair by plating

Paul D August 24, 2001 01:38PM

Re: Boiler repair by plating

Hugh Odom August 24, 2001 05:15PM



Sorry, you can't reply to this topic. It has been closed.